AS 2419.1:2017 Fire hydrant installations, Part 1: System design, installation and commissioning
Standards Australia
Supersedes: AS 2419.1-2005 AMDT 1 Fire hydrant installation, Part 1: System design, installation and commissioning
Supersedes: AS 2419.1-2005 Fire hydrant installations, Part 1: System design, installation and commissioning
Draft Designation: DR AS 2419.1:2016This Standard specifies requirements for the design, installation, commissioning and testing of fire hydrant installations. It applies to on-site fire hydrant installations, that is, fire hydrant installations used to protect buildings, structures, storage yards, marinas and associated moored vessels, wharves and plant.
Originated as AS 2419-1980. Revised and redesignated AS 2419.1-1988. Fourth edition 2005. Fifth edition 2017.
Contents:
Section 1: Scope And General
Section 2: System Performance And Design
Section 3: Hydrant Location, Coverage And Related Provisions
Section 4: Water Sources And Supply
Section 5: Water Storage Tanks
Section 6: Pumpsets
Section 7: Fire Brigade Booster Assembly
Section 8: Pipework Design And Installation
Section 9: Pipes, Valves And Fittings
Section 10: Pipe Supports
Section 11: Ancillary Equipment, Signage And Baseline Data
Section 12: Commissioning
Fire Hydrant Installations.
FP-009
Association of Accredited Certification Bodies; Association of Hydraulic Services Consultants Australia; Australasian Fire and Emergency Service Authorities Council; Australian Building Codes Board; Australian Chamber of Commerce and Industry; Australian Fire Safety Practitioner’s Accreditation Board; Australian Industry Group; Australian Institute of Building Surveyors; Australian Stainless Steel Development Association; Australian Steel Institute; Copper Development Centre Australia; Department of Defence, Australia; Engineers Australia; Fire Protection Association Australia; Insurance Council of Australia; Plastics Industry Pipe Association of Australia; Property Council of Australia; Water Services Association of Australia.